The Claim Does Not Fail on the Merits. It Fails at the Gate.
A contractor completes 18 complex site variations over fourteen months. The works were genuinely instructed by the engineer. The additional plant and overtime were spent. The physical delay to commissioning is beyond dispute.
Sub-Clause 20.1 (or 20.2 in the 2017 form): notice of claim must be served within 28 days of becoming aware of the event or circumstance, followed by a fully detailed claim within 42 days.
Out of 18 events, exactly 5 carried a compliant first-limb notice. None carried the compliant 42-day follow-on submission. The employer’s legal team filed an immediate summary determination at the threshold.
The contractor spent US$ 4.2m proving cause, effect, and disruption optics. But the arbitrator never reached the merits. The claim failed at the gate. If your record does not prove the procedural condition precedent, your engineering file is an expensive diary.
Rebuilding daily site records into a chain of evidence a tribunal can check.
Forensic schedule delay modelling, quantum substantiation, and dispute avoidance across the GCC.