Delay Is a Fact. Entitlement Is a Document.
A project manager stands in front of his board: "The employer delayed our heavy lift by 68 days. Everyone knows it. The client’s representative was on site every morning nodding his head."
Contracts do not pay for knowledge. They pay for compliant contemporaneous records. A verbal agreement or an engineer’s sympathetic nod on a site walk is hearsay when the liquidated damages letter lands.
Without a contemporaneously submitted daily log, an impact notice referencing the accepted programme, and proof of critical path occupation, the 68 days of site idling converted into 68 days of contractor-culpable overrun.
Delay is a physical fact that happens in the dust. Entitlement is a document that lives in the file. Only one of them gets paid. Rebuild the file while the works run, or prepare to discount the claim by 70% at the settlement table.
Rebuilding daily site records into a chain of evidence a tribunal can check.