CONTRACT STRUCTURE & ALLOCATION2026-01-20 · 7 min read

Who Carries What: Risk Allocation in Small Modular Reactor Contracting

Turnkey fixed-price EPC contracts broke the last generation of nuclear builds. SMR delivery requires unbundling licensor risk from balance-of-plant construction.

What is new in this piece:A structured breakdown of risk transfer models between reactor technology vendors, balance-of-plant constructors, and owner SPVs.

The Analytical Argument

No civil contractor has the balance sheet or risk tolerance to guarantee nuclear regulatory licensing timelines under a lump-sum arrangement. Trying to force fixed-price EPC onto FOAK (First of a Kind) reactor technology merely invites contractor bankruptcy or inflated risk premia that kill projects before FID.

Turnkey fixed-price EPC contracts broke the last generation of nuclear builds. SMR delivery requires unbundling licensor risk from balance-of-plant construction.

EMPIRICAL DATUM
+120%

Average cost overrun across nuclear power projects

Flyvbjerg et al. benchmark dataset (N = 196; 54.59% of nuclear power projects overrun by >50%).

PRIMARY EVIDENCE

Every figure traces to primary sources. No claims vocabulary.

Towards a Theory of Modular Natives: Explaining Superscaling (arXiv:2606.15757, Table 1)

Publisher / Authors: Flyvbjerg, Budzier & Christodoulou · As at: 2026

Project Structuring and Risk Allocation for SMR Commercial Deployment

Publisher / Authors: Electric Power Research Institute (EPRI) · As at: 2024

Author Disclosure:The author independently advises on capital-project delivery and holds no position, mandate or commercial arrangement with any party named here.