Nuclear Post

Independent capital-project delivery research. We examine technology screening, supply-chain forgings, modular learning curves, and FID readiness. Every figure traces to an explicit primary source.

6 essays, newest first.

FLEET SCALE & DELIVERY RATE2026-11-18 · 7 min read

A Speed, Not a Stock: 100 GW by 2047 as a Delivery Rate

The official roadmap expects about 22 GW of nuclear capacity by 2031–32 and aims for 100 GW by 2047. That is 78 GW to add in roughly 15 years, or about 5.2 GW a year. Capacity installed since October 1969 is about 8.8 GW, a pace well under 0.2 GW a year.

5.2 GW/yrAverage annual addition from about 22 GW in 2031–32 to 100 GW in 2047
Read full analysis
#Fleet Scale#Delivery Rate#India#Supply Chain
STATUTE & BANKABILITY2026-11-12 · 8 min read

Nine Open Points: What Still Stands Between the SHANTI Act and a Bankable Project

The SHANTI Act became law in December 2025. Draft Rules followed on 14 August 2026, and comments closed on 4 September 2026. Nine commercial papers still stand between a permitted nuclear project and one that can be financed and signed.

9Commercial papers still open between the statute and a project that can be financed and signed
Read full analysis
#SHANTI Act#Bankability#India#Pre-FID
PROCUREMENT & MARKET STRUCTURE2026-03-15 · 6 min read

One Bidder: Why Competitive Tendering Fails in Advanced Nuclear

When a capital programme requires five years of pre-investment screening and billions in licensed design commitments, standard competitive auctions collapse to single-vendor bilateral lock-ins.

1 of 4Shortlisted vendors reaching binding final pricing in contested SMR programmes
Read full analysis
#Procurement#Capital Allocation#Nuclear Economics#SMR